- Your Rights, Your Lands, Your Strong Future -
Recent Projects & Agreements
- Songhees Creek Hydro Project (IBA between Kwakiutl Band Council and Songhees Creek Hydro)
Acted for Kwakiutl Band Council (BC)
Signed January 2008
Project: 15 Megawatt Songhees Creek Run-of-River power project; capital costs approximately $45 million
- TMX Anchor Loop Project Anchor Loop Pipeline Project (Mutual Benefits Agreement between Simpcw First Nation and Kinder Morgan Canada)
Acted for Simpcw First Nation (BC)
Signed August 2007
Project: 165 km Trans Mountain Pipeline; Capital Costs: $450 Million
- Bone Creek, Serpentine and Clemina Hydroelectric Projects (IBA between Simpcw First Nation and Canadian Hydro Developers)
Acted for Simpcw First Nation (BC)
Signed August 2007
Project: 3 Run-of-River Power Projects; Capital Costs: $90 million
- Galore Creek Mining Project (Participation Agreement between Tahltan Nation and NovaGold Canada Inc.)
Acted for Tahltan Nation Central Council (BC)
Signed February 10, 2006
Project: Copper, Silver, Gold Mine in north central B.C.; Capital Cost: $4 Billion
- Victor Diamond Mine Project (Impact Benefits Agreement between Attawapiskat First Nation and De Beers Canada Inc.)
Acted for Attawapiskat First Nation (Ontario)
Signed November 4, 2005
Project: Ontario's First Diamond Mine; Capital Cost: $1.0 Billion
- Orca Sand & Gravel Project (Impact Benefits Agreement between Kwakiutl Band Council and Polaris Minerals Ltd.)
Acted for Kwakiutl Band Council (BC)
Signed February 2005
Project: 32 year large scale aggregate (sand and gravel) project on North Vancouver Island; Capital Cost: $80 million
- Kwoiek Creek Resources Limited Partnership (Limited Partnership between Kanaka Bar Indian Band and Innergex II Inc.)
Acted for Kanaka Bar Indian Band (BC)
Signed December 2004
Project: 49.9 Megawatt Run-of-the-River Hydroelectric Project in the Fraser Canyon; Capital Cost: $130 Million
work/index.htm 2009.06.25 Copyright © 2009 McDonald & Company
|